Setting up Your Project Cost Groups

Setting up Your Project Cost Groups

STRUCTURE

You already have your Cost Category Schedule in place for your Programme which provides the structure at the levels of Cost Summary Items within Cost Groups. 

What we are now looking at is the detailed cost breakdown structure of the Cost and Sub Cost Items that make up each Cost Summary Item.
  1. Identify all the cost/trade items that need to be reported against in your PCG and payment certificate reports (these cost items are those that you need to be placed within the cost group “Contract Costs”)

  2. identify under which summary items the individual cost items should be grouped remembering that you can only consolidate across projects that share the same summary items within the same cost group.

  3. Identify all your Contingency fund sources as these summary items must exist in your Client Cost Category Schedule.

  4. Group your Non-Contract/Construction costs under summary items within other cost group as suits your particular needs.

Then,

  1. Assign unique cost codes to each cost group, summary item and cost item.

  2. Set your initial budgets for each of the above items as well as forecast costs on all cost items.

  3. Check that the above cost groups and summary items exist in your Client Cost Category Schedule.


    • Related Articles

    • Defining your Client Cost Category Schedule

      You are able to define a fully customised Cost Category Schedule for each Client in WebCert once the Client has been created. This identifies ALL the Cost Groups and Cost Summary Items within of these groups that you may wish to use across ANY ...
    • Quick process for creating a new client project with assigned users

      The following steps will walk you through a quick straight forward process for creating a new project for a new client. For a complete understanding of the processes you should refer to the WebCert User Guide. The processes assume you have the ...
    • 26th November 2020 Release 4.2.0-51

      This release update included fixes to a number of issues identified with the system along with some changes to existing features to improve the processing and integrity of data held on projects.   The following changes were applied in this release. ...
    • 11th Oct 2020 - Major system update Release 4.1.0-1

      Last night a major update to the WebCErt 4 system was completed to deliver a series of feature enhancements, customisations and bug fixes. The details of the updates applied in Release 4.1.0-1 are summarised below.   Change Requests ...
    • 6th April 2021 Release 4.2.0-212

      WebCert has released a number of software updates to various modules and reports in response to some problems that have been previously identified. Included in this release, we have also included some minor improvements to various aspects of the ...